“The Greece-Bulgaria interconnector should be ready by the end of 2021 so that liquefied gas can flow through it from Alexandroupolis - American, Israeli, Egyptian, from many sources. In future its capacity can be increased to 5 billion cubic metres of gas a year,” said Prime Minister Boyko Borissov who conducted an inspection of the construction work.
The project is important for Bulgaria and for the region because if affords the possibility of diversifying natural gas supply sources, the government press service states.
At this time pipes have been distributed along the 150-km. track in preparation of subsequent activity, along 70 kilometres the pipes have been laid in trenches. The pipeline is 182 kilometres long, 150 of which on Bulgarian territory.
On Saturday, the lowest temperatures will be between 14 and 19°C; in Sofia - about 16°C. In the western regions, the highest temperature will be 19-20°C, while in the eastern regions of the country the temperature will reach up to..
The Court of Justice of the EU has overturned part of European legislation requiring trucks for international transport to return every two months to the carrier's base. With its decision, the institution confirmed all other..
There is a potential danger of a wave of migrants, caretaker Prime Minister Dimitar Glavchev said at a briefing after the meeting of the Consultative Council on National Security , at which the risks to this country stemming from the..
Charges of trading in influence are to be brought against Dzheyhan Ibryamov after decisions were made to strip him of his immunity from prosecution..
In December this year the Ministry of Finance will have covered the last of the criteria for accession to the Eurozone – inflation, said caretaker..
If the general elections were to be held at the beginning of October, 6 parties and coalitions would enter the Bulgarian parliament, a Market Links..
+359 2 9336 661