Bulgaria has sent us a request to extend the offer period for the American tankers with liquefied gas , Anton Kutev, the spokesman of the office, told BTV. In its last days, Kiril Petkov's government managed to negotiate with an American company the..
“The problem with the second gas interconnector between Greece and Bulgaria is the unfinished construction work. We are expecting a day-to-day timetable of performance of the works from the builder,” caretaker Minister of Regional Development and..
“The gas interconnector Greece-Bulgaria will be given preferential treatment in the highest degree so that it can be made operational as soon as possible,” caretaker Minister of Regional Development architect Ivan Shishkov said at a technical..
“If the needs and demands exceed the capacity of the Greece-Bulgaria gas interconnector at Komotini, which amounts to 5 billion cubic metres of gas annually, it is possible to build a second pipe that would meet the growing demand,” Teodora..
Outgoing Prime Minister Kiril Petkov announced, at a briefing, that the gas interconnector Greece-Bulgaria, which will be used to transport gas from Azerbaijan to Bulgaria, now has Act 14 (the first step of control of construction works) , and that..
With the commissioning of the interconnector with Greece, Bulgaria will be able to receive natural gas from Azerbaijan in full volumes, Azerbaijan’s ambassador to Bulgaria Huseyn Huseynov said in an interview for the Azeri news outlet Trend News..
The gas interconnector with Greece should become part of the strategic objects of importance for our national security - this is what Bulgarian Ministry of Energy has insisted to the Council of Ministers. "The facility has become of paramount..
“92% of the Gas Interconnector Greece-Bulgaria, ICGB, is ready. The interconnector will be ready by the end of June, and will be tested with gas as of July,” Teodora Georgieva, Bulgarian Executive Officer of the company ICGB which is constructing..
The interconnector with Greece near Komotini is expected to be completed by the end of June and the Azeri gas to flow through it to Bulgaria in September , Prime Minister Kiril Petkov, who inspected the gas route today, said. According to PM..
“The Greece-Bulgaria interconnector should be ready by the end of 2021 so that liquefied gas can flow through it from Alexandroupolis - American, Israeli, Egyptian, from many sources. In future its capacity can be increased to 5 billion cubic metres..