Eмисия новини
от 12.00 часа

ContourGlobal Maritsa East 3 TPP shutdown after contract with NEC expires

The thermal power plant (TPP) ContourGlobal Maritsa East 3 - one of the two so-called American power plants - has ceased operations. The reason is the expiry of the long-term contract with the National Electricity Company for the purchase of electricity..

21.02.24 13:53 |
Maritsa Iztok 2 TPP

Bulgaria has arguments against the closure of the TPP, but no one to communicate them, Bulgarian Energy and Mining Forum Chair says

"Bulgaria has strong arguments for postponing the shutdown of coal plants until at least 2030. We are facing a serious energy crisis, a regional deficit. " This is what Ivan Hinovski, energy expert and chairman of the Bulgarian Energy and Mining Forum,..

29.03.23 15:15 |
Bobov Dol TPP

Todor Galev: There is evidence of a protective umbrella over the falsification of data regarding TPP greenhouse gas emissions

“There is evidence that certain people in high public positions have been opening a protective umbrella over the falsification of data regarding greenhouse gas emissions, or have at least failed to probe shady deals,” Todor Galev from the Centre..

01.03.23 13:10 |
Maritsa East 2 coal-fired power plant

Bulgaria does not want to give up coal until 2038

The last Bulgarian Parliament obliged the Council of Ministers to amend the National Recovery and Resilience Plan in the field of energy. The main change is to keep the coal-fired power plants operating until at least 2038. With the adopted..

27.02.23 18:31 |
Interior Minister Ivan Demerdzhiev

European Prosecutor's Office conducts action in Bulgaria

Currently, an action is being held in Bulgaria by the European Public Prosecutor's Office , BTA reported. Bulgaria's caretaker Interior Minister Ivan Demerdzhiev confirmed the information and added that the materials relating to the operation would be..

27.02.23 14:11 |

"Maritsa East 3" TPP temporarily stopped because of repeated environmental violations

The Bulgarian authorities temporarily closed the "Maritsa 3" TPP near Dimitrovgrad after a series of violations of environmental norms. "They literally committed eight violations from Friday to Saturday out of the 24 allowed for all..

13.09.22 15:05 |
The Maritsa-Iztok 3 TPP

Maritsa-Iztok 3 coal-fired power plant reopens after being closed over air pollution

Maritsa-Iztok 3 coal-fired power plant in Dimitrovgrad has been functioning since last night, BNR’s correspondent Dora Atanassova reports. Maritza Iztok-3 TPP, closed due to systemic pollution, will not resume work, Environment Minister says..

10.06.22 14:48 |
Environment Minister Borislav Sandov

Until it puts in place air purification improvements, Maritza Iztok-3 TPP will not resume work, Environment Minister says

“Because of the costly emission quotas, coal-fired thermal power plants may have to close down for economic reasons,” Minister of Environment and Water Borislav Sandov stated in Blagoevgrad. Maritza Iztok-3 TPP, closed due to systemic..

14.05.22 15:42 |
Environment Minister Borislav Sandov

Maritza Iztok-3 TPP, closed due to systemic pollution, will not resume work, Environment Minister says

The EU Court of Justice has ruled that Bulgaria has not fulfilled its commitments under the quality of atmospheric air directive. If Bulgaria fails to change this state of affairs, the EU could, once again, file a suit against the country and impose..

12.05.22 14:12 |

Supreme Administrative Court orders Environment Ministry to pay private TPP Brikel 25 million Leva

By force of a Supreme Administrative Court ruling, the Ministry of the Environment and Water has been ordered to pay 25 million Leva (EUR 12.8 million) in compensation to the private thermal power station Brikel, which is connected with businessman..