Government and Westinghouse still negotiating 7th unit’s financial model

БНР Новини
Photo: BGNES

The events from the recent days have reminded that Bulgaria puts efforts in its nuclear energy sector as well, as far as diversification is concerned. The negotiations with the US Westinghouse company for the construction of a new AP1000 nuclear reactor with the future 7th unit of the Kozloduy NPP are ongoing. The facility will cost some EUR 4.7 billion at an overall price of around EUR 6.9 billion for the entire unit. The preliminary estimations on the price and the project’s potential were grounded on a shareholder agreement between the energy company and the Bulgarian Energy Holding /BEH/, signed mid-2014. Westinghouse’s Vice President Aziz Dag reported the data during a discussion, named Energy Security and Accessibility via Energy Diversification.

Aziz Dag commented the ongoing modernization of the Kozloduy NPP’s 5th and 6th units like that:

“The rehabilitation of the 5th and 6th units of Kozloduy to the tune of some EUR 89 million has been funded by the US Ex-Im Bank, as we hope to deepen our partnership in the energy sector also under the construction of the plant’s 7th unit.”

This statement comes to show that the Ex-Im Bank could be the potential financial partner for the project on the 7th unit, in case of an approval.

“Incomes from electricity export over the next 20 years will come up to the tune of some EUR 11.1 billion, if the government and Westinghouse finalize the contract. That makes the new power very profitable in terms of economy,” Mr. Dag further commented.

Currently Bulgaria exports electricity to Turkey and that, according to Westinghouse’s energy experts, won’t change despite the 4 nuclear units that are being constructed by our southern neighbor under a Russian project. Those won’t be able to cover Turkey’s growing needs, which annually imports electricity worth around EUR 53.3 billion.

The project’s implementation will lead to the opening of more than 20,000 new jobs and this will reduce the level of unemployment here by some 4 percent, keeping manpower in northwest Bulgaria, the US polls go on to show.

The basic price for the electricity, produced by the plant over the next 60 years, including building, fuel-providing and maintenance expenses will be around EUR 67 per megawatt hour.

At the moment Kozloduy works at EUR 30 per megawatt hour, which can be explained with the fact that the 5th and 6th units were built up more than two decades ago, at lower prices. To compare, the estimations of Rosenergoatom on the ceased Belene NPP project showed a basic price of around EUR 75 per megawatt hour.

The shareholder agreement, signed during the final days of the Oresharski cabinet envisages the shares within the new company – Kozloduy NPP – New Powers to be divided like that: 70 percent for the Kozloduy NPP and 30 percent for Westinghouse. The company is to deliver and install the unit, withdrawing from the project after the end of the construction activities – the state and the plant will remain the owners of all. PM Boyko Borissov has stated several times that he sees any sense in the project if Westinghouse enters it as an investor. In the words of Vice President Strategy and External Relations Europe, Middle East and Africa of Westinghouse Michael Kirst, currently there are ongoing negotiations with the Bulgarian state for determining the financial model.

“In December /2014/ we formed a working group with the new government, aiming at the continuity and approval of the project. Regarding nuclear energy, Bulgaria has as many points of view, as the number of people with any points of view.”

The final investment decision for the project is expected to be made by 2018 – 2019. Thus the new facility will be able to start working around 2025.

English version: Zhivko Stanchev




Последвайте ни и в Google News Showcase, за да научите най-важното от деня!
Listen to the daily news from Bulgaria presented in "Bulgaria Today" podcast, available in Spotify.

More from category

The Institute for Market Economics calls for budget deficit below 3%

We are moving towards the option of not having a quickly adopted budget for 2025, Lachezar Bogdanov, chief economist from the Institute for Market Economics, told BNR.  In presenting the institute's alternative state budget, the..

published on 11/4/24 11:27 AM

The five largest Indian IT companies already have offices in Bulgaria

Bulgaria and India will intensify their cooperation in various sectors of mutual interest. This was discussed at a meeting of the Bulgarian Minister of Economy Petko Nikolov with Ambassador of India to Bulgaria H.E. Sanjay Rana. The two focused..

published on 10/31/24 5:48 PM

A Bulgarian-Czech Chamber of Commerce established in Sofia

On October 31, 2024, 10 business leaders in Bulgaria founded the first Bulgarian-Czech Chamber of Commerce in the country. At the Embassy of the Czech Republic in Sofia, in the presence of Martin Dvořák, Minister of European Affairs of the Czech..

published on 10/31/24 1:54 PM